{"id":31031,"date":"2018-07-11T05:17:46","date_gmt":"2018-07-11T09:17:46","guid":{"rendered":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/?p=31031"},"modified":"2018-07-12T09:58:24","modified_gmt":"2018-07-12T13:58:24","slug":"business-report-5-construction-contract-considerations","status":"publish","type":"post","link":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/","title":{"rendered":"Business Report: 5 Construction Contract Considerations"},"content":{"rendered":"
\"\"
John Frega, Esq., is an attorney with Bond, Schoeneck & King<\/figcaption><\/figure>\n

By John Frega, esq.<\/p>\n

Every construction project features unique and interesting challenges. But drafting your construction contract documents should not be one of those challenges.\u00a0<\/span><\/p>\n

Here are five important matters to consider when drafting and managing your construction contracts:<\/p>\n

1. Determine the appropriate payment model.\u00a0<\/span><\/p>\n

<\/p>\n

Owners have multiple options for structuring payments to their contractors, and choosing the appropriate payment model largely depends on the type of project. The most common models include lump sum, unit price, and time and material, not to exceed (T&M NTE).<\/p>\n

Under the lump sum model, the parties agree to a total, fixed price to be paid for all work under the contract. Lump sum pricing is appropriate for projects with a well-defined scope of work and clear schedule, such as residential homes or commercial buildings.<\/p>\n

Under the unit price model, the scope of work is broken into discrete units and prices are established for each unit of work. This model is often used in public projects, such as highway construction or utility construction.<\/p>\n

Using the T&M NTE model, the contractor is paid for the actual time spent on the project at rates agreed to by the parties, and is reimbursed for the cost of materials used in the project. The total amount of compensation payable to the contractor is capped at the \u201cnot to exceed\u201d amount established in the contract.\u00a0<\/span><\/p>\n

This model is commonly used in architecture and engineering contracts, as well as in construction where a lump sum or unit price model cannot be used.<\/p>\n

2. Surety bonds and why they are important. \u00a0<\/span><\/p>\n

Every construction project contains inherent risk. This includes the risk that a contractor will be unable to complete the project, and the risk that the contractor will be unable to keep up with payments to its subcontractors and material suppliers. The most common method of minimizing this risk is to require the contractor to procure and maintain construction-related bonds, specifically a performance bond and a payment bond. \u00a0<\/span><\/p>\n

A third party that guarantees the performance of the contractor, in the event that the contractor is unable to complete the project, issues the performance bond.<\/p>\n

The payment bond guarantees that subcontractors and material suppliers will receive the amounts due and owing from the contractor in the event the contractor is unable to make these payments. It is important to ensure that payments are made to subcontractors and material suppliers in order to prevent these entities from asserting liens against the owner\u2019s property.<\/p>\n

3. Indemnification and its limits.\u00a0<\/span><\/p>\n

Another method of minimizing an owner\u2019s risk is the inclusion of an indemnification provision in the contract. An indemnification provision in favor of an owner requires the contractor to compensate the owner for liabilities or losses that the owner incurs as a result of the contractor\u2019s actions during the project.\u00a0<\/span><\/p>\n

In most instances, these liabilities and losses are in the form of claims brought by third parties (such as construction workers or owners of property adjacent to the project site) for personal injuries or property damage. New York law limits the scope of indemnification provisions. Namely, the project owner cannot be indemnified for personal injury or property damage claims that are the result of the owner\u2019s own negligence or intentional wrongdoing.\u00a0 \u00a0<\/span><\/p>\n

4. Managing \u201cextra\u201d work issues.\u00a0<\/span><\/p>\n

During the course of the project, a need often arises to alter the scope of the project. These alterations most often come in the form of additional, or \u201cextra,\u201d work. Disputes regularly develop between owners and contractors in connection with \u201cextra\u201d work claims.\u00a0<\/span><\/p>\n

Often, the parties disagree over what constitutes \u201cextra\u201d work and the amount of compensation due to the contractor for this \u201cextra\u201d work. While disputes cannot be entirely avoided, the number and impact of these disputes can be managed through\u00a0<\/span><\/p>\n

First, the parties should strive to draft a clear and well-defined scope of work at the outset of the project. Clearly defining the scope of work may reduce the overall number of \u201cextra\u201d work claims. Further, where the parties agree that there is a need to perform \u201cextra\u201d work, the parties should strive to clearly define the scope and compensation for this work in written change orders, and stipulate that a change order must be executed by the parties prior to performing any \u201cextra\u201d work. \u00a0<\/span><\/p>\n

5. Delays and no damage for delay.\u00a0<\/span><\/p>\n

Delays hamper the completion of many construction projects, often through no fault of either party. The parties then struggle to determine who will bear the risk of these delays. Project owners can minimize these risks through the use of a \u201cno damage for delay\u201d clause.\u00a0<\/span><\/p>\n

These clauses provide that a contractor\u2019s remedies in the event of a delay will be limited to an extension of time to complete the project, equal to the length of the delay. A \u201cno damage for delay\u201d clause has its limits, however. Notably, the clause will not apply where the delays are the result of the owner\u2019s material breach of the construction contract, or where the delays are caused by the owner\u2019s active interference, gross negligence, or willful misconduct.<\/p>\n

Frega is an attorney with Bond, Schoeneck & King who practices business and commercial law and advises clients on transactional and litigated matters.<\/i><\/p>\n","protected":false},"excerpt":{"rendered":"

By John Frega, esq. Every construction project features unique and interesting challenges. But drafting your construction contract documents should not be one of those challenges.\u00a0 Here are five important matters to consider when drafting and managing your construction contracts: 1. Determine the appropriate payment model.\u00a0<\/p>\n","protected":false},"author":89,"featured_media":0,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[49],"tags":[],"yoast_head":"\r\nBusiness Report: 5 Construction Contract Considerations - Glens Falls Business Journal<\/title>\r\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\r\n<link rel=\"canonical\" href=\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/\" \/>\r\n<meta property=\"og:locale\" content=\"en_US\" \/>\r\n<meta property=\"og:type\" content=\"article\" \/>\r\n<meta property=\"og:title\" content=\"Business Report: 5 Construction Contract Considerations - Glens Falls Business Journal\" \/>\r\n<meta property=\"og:description\" content=\"By John Frega, esq. Every construction project features unique and interesting challenges. But drafting your construction contract documents should not be one of those challenges.\u00a0 Here are five important matters to consider when drafting and managing your construction contracts: 1. Determine the appropriate payment model.\u00a0\" \/>\r\n<meta property=\"og:url\" content=\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/\" \/>\r\n<meta property=\"og:site_name\" content=\"Glens Falls Business Journal\" \/>\r\n<meta property=\"article:published_time\" content=\"2018-07-11T09:17:46+00:00\" \/>\r\n<meta property=\"article:modified_time\" content=\"2018-07-12T13:58:24+00:00\" \/>\r\n<meta property=\"og:image\" content=\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-content\/uploads\/sites\/109\/2018\/07\/construction-column-frega-c-195x300.jpg\" \/>\r\n<meta name=\"author\" content=\"Jake Van Ness\" \/>\r\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\r\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Jake Van Ness\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"5 minutes\" \/>\r\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/\",\"url\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/\",\"name\":\"Business Report: 5 Construction Contract Considerations - Glens Falls Business Journal\",\"isPartOf\":{\"@id\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#website\"},\"datePublished\":\"2018-07-11T09:17:46+00:00\",\"dateModified\":\"2018-07-12T13:58:24+00:00\",\"author\":{\"@id\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#\/schema\/person\/a11ec438b5f0e57f1156754ba3931b86\"},\"breadcrumb\":{\"@id\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/\"]}]},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Business Report: 5 Construction Contract Considerations\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#website\",\"url\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/\",\"name\":\"Glens Falls Business Journal\",\"description\":\"\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/?s={search_term_string}\"},\"query-input\":\"required name=search_term_string\"}],\"inLanguage\":\"en-US\"},{\"@type\":\"Person\",\"@id\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#\/schema\/person\/a11ec438b5f0e57f1156754ba3931b86\",\"name\":\"Jake Van Ness\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/8083519989e12032abdd06a668982ef4?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/8083519989e12032abdd06a668982ef4?s=96&d=mm&r=g\",\"caption\":\"Jake Van Ness\"},\"url\":\"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/author\/jakev\/\"}]}<\/script>\r\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Business Report: 5 Construction Contract Considerations - Glens Falls Business Journal","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/","og_locale":"en_US","og_type":"article","og_title":"Business Report: 5 Construction Contract Considerations - Glens Falls Business Journal","og_description":"By John Frega, esq. Every construction project features unique and interesting challenges. But drafting your construction contract documents should not be one of those challenges.\u00a0 Here are five important matters to consider when drafting and managing your construction contracts: 1. Determine the appropriate payment model.\u00a0","og_url":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/","og_site_name":"Glens Falls Business Journal","article_published_time":"2018-07-11T09:17:46+00:00","article_modified_time":"2018-07-12T13:58:24+00:00","og_image":[{"url":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-content\/uploads\/sites\/109\/2018\/07\/construction-column-frega-c-195x300.jpg"}],"author":"Jake Van Ness","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Jake Van Ness","Est. reading time":"5 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/","url":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/","name":"Business Report: 5 Construction Contract Considerations - Glens Falls Business Journal","isPartOf":{"@id":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#website"},"datePublished":"2018-07-11T09:17:46+00:00","dateModified":"2018-07-12T13:58:24+00:00","author":{"@id":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#\/schema\/person\/a11ec438b5f0e57f1156754ba3931b86"},"breadcrumb":{"@id":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/"]}]},{"@type":"BreadcrumbList","@id":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/2018\/07\/business-report-5-construction-contract-considerations\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/"},{"@type":"ListItem","position":2,"name":"Business Report: 5 Construction Contract Considerations"}]},{"@type":"WebSite","@id":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#website","url":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/","name":"Glens Falls Business Journal","description":"","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/?s={search_term_string}"},"query-input":"required name=search_term_string"}],"inLanguage":"en-US"},{"@type":"Person","@id":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#\/schema\/person\/a11ec438b5f0e57f1156754ba3931b86","name":"Jake Van Ness","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/8083519989e12032abdd06a668982ef4?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/8083519989e12032abdd06a668982ef4?s=96&d=mm&r=g","caption":"Jake Van Ness"},"url":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/author\/jakev\/"}]}},"_links":{"self":[{"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/posts\/31031"}],"collection":[{"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/users\/89"}],"replies":[{"embeddable":true,"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/comments?post=31031"}],"version-history":[{"count":1,"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/posts\/31031\/revisions"}],"predecessor-version":[{"id":31033,"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/posts\/31031\/revisions\/31033"}],"wp:attachment":[{"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/media?parent=31031"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/categories?post=31031"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.glensfalls.com\/glensfallsbusinessjournal\/wp-json\/wp\/v2\/tags?post=31031"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}